NOTICE TO MARINERS NO.50/2021T
ANNOUNCEMENT TO THE SHIPPING TRAFFIC
OFF THE COAST OF SURINAME
CHART 2014
SHIP TO SHIP TRANSFER

With reference to NtM NO.42/2021T, regarding ship-to-ship transfer off the coast of Suriname, you are informed that the ship to ship transfer is extended until July 25th, 2021.

All ships should take notice of the above mentioned.

NOTICE TO MARINERS NO.49/2021T
ANNOUNCEMENT TO THE SHIPPING TRAFFIC
CHART 2219
COTTICA RIVER
PASSAGE VESSEL

On the 10th and 11th of July 2021 the MV ACE (02679) shall sail from Alkmaar to Traymore port facility and back, supported by the tugboat KULDIPSINGH 01. The ship will pass the villages along the Cottica River as follows:
1. On July 10th, 2021 between 05:00 – 17:00 hour from Alkmaar to Traymore port facility.
2. On July 11th, 2021 between 07:00 – 18:00 hour from Traymore port facility to Alkmaar.

Communication is through VHF channel 12.

The public should take notice of the above mentioned.

NOTICE TO MARINERS NO.48/2021T
ANNOUNCEMENT TO THE SHIPPING TRAFFIC
CHART 2765
SURINAME RIVER, DIJKVELDBANK
DREDGING ACTIVITIES TOUT LUI FAUT JETTY

From 3rd till 6th of July 2021 dredging activities will take place alongside the left bank of the Suriname River at the south end of the "Staatsolie Tout Lui Faut Jetty" with pontoons and tugboats at the position 05° 45’.95 N – 055° 08’.67 W (WGS 84).

The dredged material will be dumped at a privately owned land near Staatsolie Tout Lui Faut at the left bank of the Suriname River.
The operations will take place during daytime.

Communication is through VHF channel 12.

All ships should take notice of the above mentioned.

NOTICE TO MARINERS NO.47/2021T
ANNOUNCEMENT TO THE SHIPPING TRAFFIC
CHART 2765
SURINAME RIVER, DIJKVELDBANK
DREDGING ACTIVITIES VABI PORT FACILITY

From July 1st till the 30th of September 2021 dredging activities will take place alongside the left bank of the Suriname River at the “Vabi Port Facility” with pontoons and tugboats.

The working area is indicated by the following coordinates in WGS 84:
           Latitude       Longitude
A   05° 46’.433 N   055° 09’.116 W
B   05° 46’.516 N   055° 09’.200 W

The dredged material will be dumped at a privately owned land near plantation Rust & Werk at the right bank of the Commewijne River.
The operations will take place during daytime.

Communication is through VHF channel 12.

All ships should take notice of the above mentioned.

NOTICE TO MARINERS NO.45/2021T
ANNOUNCEMENT TO THE SHIPPING TRAFFIC
MEASURES OF THE MAS WITH REGARD TO COVID-19
INSPECTION OF VESSELS

Due to the current COVID-19 situation, the inspection of vessels will take place remotely via video call from June 14 until further notice. The programs that will be used are WhatsApp, Google meet or Microsoft Teams.

For further information, please contact Mr. C. Finisie:
Mobile: 8722099 or via email: This email address is being protected from spambots. You need JavaScript enabled to view it..

Kindly take the above into account.

NOTICE TO MARINERS NO.44/2021T
ANNOUNCEMENT TO THE SHIPPING TRAFFIC
CHART 2219
COTTICA RIVER
PASSAGE VESSEL

On the 15th and 16th of June 2021 the MV AMA (02670) shall sail from Alkmaar to Traymore port facility and back. The ship will pass the villages along the Cottica River as follows:
1. On June 15th, 2021 between 05:00 – 17:00 hour from Alkmaar to Traymore port facility.
2. On June 16th, 2021 between 07:00 – 18:00 hour from Traymore port facility to Alkmaar.

Communication is through VHF channel 12.

The public should take notice of the above mentioned.

NOTICE TO MARINERS NO.43/2021T
ANNOUNCEMENT TO THE SHIPPING TRAFFIC
CHART 2017
OFF THE COAST OF SURINAME
EXPLORATION DRILLING

With reference to NtM NO.10/2021T, regarding exploration drilling off the Coast of Suriname at the drilling location 07° 25’.5 N – 056° 00’.5 W (WGS 84), you are informed that the drillship Maersk Valiant has extended his operations until July 31st ,2021.

For safety reason vessels should keep a safe distance of 1000 (one thousand) meters from the drillship.

Please note:
• Communication is through VHF channels 16 and 77.
• There is a SAFETY ZONE of 1000 (one thousand) meters from the drilling site.
• Maersk Valiant is not maneuverable and will display the relevant characters.

All ships should take notice of the above mentioned.

NOTICE TO MARINERS NO.42/2021T
ANNOUNCEMENT TO THE SHIPPING TRAFFIC
OFF THE COAST OF SURINAME
CHART 2014
SHIP TO SHIP TRANSFER

From 10th June till 15thJuly 2021, ship to ship transfer will take place off the coast of Suriname. Round logs will be transferred from the barges Big Hub 12 and Big Hub 17 to the MV Tong Ji Men. The barges will be towed by the tugboats Massive 3 and Massive 6.

The operation area is indicated by the following coordinates:
WGS ‘84   Latitude          Longitude
D1          06° 11'.988 N   055° 19'.739 W
D2          06° 11'.988 N   055° 19'.956 W
D3          06° 11'.773 N   055° 19'.956 W
D4          06° 11'.770 N   055° 19'.739 W

The vessels will be limited in maneuverability during this operation.

Communication will be through VHF channel 12.

All ships should approach the above-mentioned area with caution and reduce speed while passing.

NOTICE TO MARINERS NO.41/2021T
ANNOUNCEMENT TO THE SHIPPING TRAFFIC
CHART 2219
COTTICA RIVER
PASSAGE VESSEL

On the 4th and 5th of June 2021 the MV ACE (02669) shall sail from Alkmaar to Traymore port facility and back. The ship will pass the villages along the Cottica River as follows:
1. On June 4th, 2021, between 05:00 – 17:00 hour from Alkmaar to Traymore port facility.
2. On June 5th, 2021, between 07:00 – 18:00 hour from Traymore port facility to Alkmaar.

Communication is through VHF channel 12.

The public should take notice of the above mentioned.

 

NOTICE TO MARINERS NO.40/2021T
ANNOUNCEMENT TO THE SHIPPING TRAFFIC
CHART 2017
OFF THE COAST OF SURINAME
EXPLORATION DRILLING

With reference to NtM NO.8/2021T, regarding exploration drilling by the drilling rig Maersk Developer, the public is informed that the drilling rig will be moved to the drilling site 07 ° 20'.600 N - 055 ° 57'.100 W (WGS 84). The drilling rig will conduct exploration drilling off the coast of Suriname from May 31st till September 30th, 2021 at this site.

For safety reasons vessels should keep a safe distance of 1000 (one thousand) meters from the drilling rig.
The Offshore Support Vessels (OSV) that will assist during the operations are MV Bourbon Topaz, MV Brad Dartez, MV Felton Tide and MV Delta Monarch.

Please note:
• Communication is through the VHF channels 16 and 77.
• There is a SAFETY ZONE of 1000 (one thousand) meters from the drilling site.
• Maersk Developer is not maneuverable and will display the relevant characters.

All ships should take notice of the above mentioned.

NOTICE TO MARINERS NO.39/2021T
ANNOUNCEMENT TO THE SHIPPING TRAFFIC
ENTRANCE SURINAME RIVER – VICINITY BUOY S6A
OBSTRUCTION FAIRWAY LIFTED

With reference to NtM no.38/2021T, regarding the vessel SALAMINA I which ran aground on position 5°59.395'N and 55° 12.976 W in the vicinity of buoy S6A, the public is informed that the fairway is no longer obstructed.

NOTICE TO MARINERS NO.38/2021T
ANNOUNCEMENT TO THE SHIPPING TRAFFIC
SURINAME RIVER
SHIP AGROUND

In the entrance of the Suriname River near buoy S6A the vessel SALAMINA I has run aground on position 5°59.395'N and 55° 12.976 W.
The fairway near the ship is currently obstructed and passage is not possible in the area mentioned above.

In the above-mentioned area the depth on the west side of the fairway is two and a half (2.5) meters at low water. Ships and crafts with less draught can pass on the west side at fifty (50) meters up to one hundred (100) meters from the vessel SALAMINA I and take in to account the tidal height at time of passage and an under-keel clearance of 0.30 meters.

For safety reasons, all ships should approach the area with caution, reduce speed and keep a clear distance of fifty (50) meters from the SALAMINA I.

NOTICE TO MARINERS NO.37/2021T
ANNOUNCEMENT TO THE SHIPPING TRAFFIC
CHART 2765
SURINAME RIVER, DIJKVELDBANK
DREDGING ACTIVITIES VABI PORT FACILITY

With reference to NtM NO.35/2021T, concerning dredging activities alongside the left bank of the Suriname River at the “Vabi Port Facility” by the dredging vessel ELBE, the shipping is informed that the dredging activities will continue from the 22nd till the 25th of May 2021.

Communication is through VHF channel 12.

All ships should take notice of the above mentioned.

NOTICE TO MARINERS NO.36/2021T
ANNOUNCEMENT TO THE SHIPPING TRAFFIC
CHART 2765
SURINAME RIVER, DIJKVELDBANK
DREDGING ACTIVITIES TOUT LUI FAUT JETTY

With reference to NtM NO.32/2021T, concerning dredging activities alongside the left bank of the Suriname River at the jetty of "Staatsolie Tout Lui Faut Jetty", the shipping is informed that the dredging activities will continue from the 21st till the 24th of May 2021.

The operations will take place around the clock (24 hours).

Communication is through VHF channel 12.

All ships should take notice of the above mentioned.

NOTICE TO MARINERS NO.35/2021T
ANNOUNCEMENT TO THE SHIPPING TRAFFIC
CHART 2765
SURINAME RIVER, DIJKVELDBANK
DREDGING ACTIVITIES VABI PORT FACILITY

On the 20th and 21st of May 2021 dredging activities will take place alongside the left bank of the Suriname River at the “Vabi Port Facility” by the dredging vessel ELBE.

The working area is indicated by the following coordinates in WGS 84:
        Latitude       Longitude
A  05° 46’.516 N  055° 09’.183 W
B  05° 46’.433 N  055° 09’.050 W

Dredging will be done by the Trailing Suction Hopper Elbe, which will suck the dredged material from the river bottom. The dredged material will be dumped on the western side of the entrance of the Suriname River outside the navigation channel.

The operations will take place around the clock (24 hours). The dredging vessel ELBE will be restricted in maneuverability during dredging.

Communication is through VHF channel 12.

All ships should take notice of the above mentioned.